Hydroelectric power plant with 4 generators
Renewal of the electrical and I&C equipment for a run-of-river power plant with three Straflo turbines and one bevel gear turbine and flow control (OW/Q).

Control system:
- 4 x SIMATIC S7-400 (for the 4x turbines)
- Integrated KIMA turbine controller (KTC)
- 1 x SIMATIC S7-400
- For weir control and general control tasks
- Telecontrol communication via IEC104
- 1 x SIMATIC S7-400
- For OW/Q (control flow control)
- Telecontrol communication via IEC104
- 2 x SIMATIC S7-1500
- For the basic drains
Operating and monitoring system:
- WinCC V7
-
- 2 x redundant WinCC stations for local operation and monitoring in the power plant for automatic and manual operation as well as measurement data recording
Bus systems:
- Industrial Ethernet
- in the optical, redundant ring
- Communication between SIMATIC S7 controllers and with the B&B system
- Telecontrol protocol IEC 60870-5-104 for simultaneous communication with 3 control centers
- Profibus:
- Decentralized periphery for signal acquisition and control of auxiliary operations
- Decentralized periphery for signal acquisition and control of existing 400 VAC supply
- Decentralized periphery for signal acquisition and control of existing MS system
Noteworthy aspects:
- Time stamping of the messages with a resolution of 3ms
- Delivery and installation of a DC supply with battery system and inverter
- Integration of the existing levels